Originally Posted by
DJ-Jokes
My electrical knowledge is limited, but I'm responsible for reviewing some testing practices for our company and trying to standardize them. We have a few product lines that we conduct our functional testing cycle followed by a HiPOT test, and a few other product lines where we HiPOT test it first and then do our functional testing.
I'm trying to understand if there is a standard practice of running the insulation testing after or before other tests due to the possibility of one set of tests affecting the other set of tests. These are all AC units and we are conducting an AC HiPOT test.
Any help in understanding what the best practices would be is appreciated.
Cheers.
----------------------------------
It has now been about 3 months I don't seem to be getting the type of advice that I am looking for, so let me start again.
I have units that in the field will have operating conditions of:
Either 120V or 240V AC
less than 2A draw
Think of it as a speed controlled window fan for all intensive purposes.
Some of the common components used are:
120V or 240V C frame 1.2A motors
SPT-2 and SPT-3 wire (aka "lampcord")
UL3173 XLPE 18g wire
Various 18g insulated connectors
Various mechanical switches
Various rheostats
I have two options for testing to try to standardize and do not understand the implications of running each test sequence.
Option A:
Apply either 120V or 240V power as appropriate to check all switch routings and "run" functionality (5 to 30 second run time).
Apply an AC HiPOT test to confirm insulation does not "leak".
Concern: In this scenerio it appears that the HiPOT test could (in very rare cases) burn out the unit and by not running the functional test first could cause a dead unit to get to our customers.
Option B:
Apply an AC HiPOT test to confirm insulation does not "leak".
Apply either 120V or 240V power as appropriate to check all switch routings and "run" functionality (5 to 30 second run time).
Concern: In this scenerio it appears that the application of power could cause a situation where the HiPOT test would fail if rerun. My opinion of this is primarially due to the run time of the motor and the switching process.
I am trying to understand:
Which (A or B) has the least risk of a failure getting past the testing.
If there is a "standard" method for order of test application based on the stresses / failures that could be missed after each test.
Cheers.