Originally Posted by
BRAD2121
Thoughts on this?
A utility defines their horizontal bus at the customer point as ABC left to right facing the customer with ABC rotation. The customer defines their buses as ABC left to right facing the utility but with CBA rotation. For a first time connection the customer has to:
A: Swap A & B phases and leave phase sequence alone
B: Swap B & C phases and leave phase sequence alone
C: Leave phasing alone and change phase sequence to ABC
D: leave phasing and phase sequence alone.
I guessed D because and don't know if I'm right. Is there a proper procedure here? Explain if possible.