Before acceptance testing begins, what steps should be taken as part of the commissioning process?
Before acceptance testing begins, what steps should be taken as part of the commissioning process?
A. Inspect devices for proper settings and installation completeness - Possible, however the question states "before acceptance testing begins" which implies that once testing begins, settings are going to get changed around and components are going to get un-wired - all of which will need to be checked upon completion. Usually the last thing we do for acceptance testing is a final visual inspection and settings check.
B. Perform a seismic drop test on each device to be installed - Um, no.
C. Inspect devices for variations from design specifications - Like I stated earlier, almost everything in NETA-ATS starts with "compare equipment to drawings and specifications". You need to be sure the correct equipment is in place before testing it.
D. B and C - Nope.
E. A and C - Possible but I personally lean towards C only.